End of School Day on DAY 1, February 17, 2021
Week of February 22-26
March 10, 2021
Pouring foundations for walls!!!
Tuesday, March 23, 2021
Pouring foundations for floors
This picture was taken around 3:30 p.m. By 7 the next morning, they had poured the concrete.
March 24, 2021
These were taken around 7 a.m.
Our Classroom
About 7 a.m. Wednesday, March 24, 2021
I asked the project manager if they could cut windows in the window coverings so we could watch what they were doing at the end of our hallway today. (Still March 24)
Taken about 9:45, Wednesday, March 24
Video shot around 1:00 on March 24
End of the school day, around 3:30 on March 24. This was taken right outside our fifth grade hallway.
March 30, 2021
Wednesday, March 31, 7:15 am
April 12 , 2021
The day after Spring Break.
Outside our classroom window at 3:10.
Tuesday, April 12, 2021 7:30 a.m.
Friday, April 16
Point of Interest...
We noticed that the bricks in our hallway are stacked. This is different from the wall going up outside our window which seems to be in towers. When Mr. Hodges asked the construction manager about it, he was told they are just following the pattern that is standard in our hallways. The new hall is all running blocks or in towers, as we called it. Our hallway is built in stack blocks all the way down.
our hallway
The New Building
May 20, 2021 7 a.m.
Shortly after the above video was taken, they covered our door.
April 21, 2021 Outside our window around 9 a.m.
Thursday, April 22, 2021: Taken through our window around 7:15
Friday, April 23, 2021
Around 7 a.m.
Later that same day...
April 27, 2021
April 28, 2021 There's a crane outside our window!
May 7, 2021
The view through the door of the fifth grade hallway.
May 17, 2021